UDOT says the new US-6 and US-89 interchange at Thistle Junction in Spanish Fork Canyon opens by Nov. 30, ending the left turn tied to 8 deaths since 2003.

The new interchange at Thistle Junction, where US-89 splits from US-6 in Spanish Fork Canyon, will open to traffic by Monday, Nov. 30, 2026, the Utah Department of Transportation said Thursday. UDOT marked the milestone on Nov. 12 with an event for families who lost relatives in crashes at the old intersection. The project replaces a T intersection, and the left turn from US-89 onto US-6 that UDOT says has been part of five fatal crashes and eight deaths since 2003, with a bridge, an underpass and on- and off-ramps.

For drivers from Utah Valley headed to Price, Moab, Manti or the Sanpete County towns, it should mean an end to the one-lane squeeze that has slowed US-6 near the junction since May, and a safer way through the canyon before the worst of winter.

Item Detail
What New grade-separated interchange at US-6 and US-89
Where Thistle Junction, Spanish Fork Canyon
Opening By Mon., Nov. 30, 2026 (UDOT); weather could affect timing
How it works US-6 crosses over US-89; ramps with longer merge lanes
Why 5 crashes, 8 deaths at or near the junction since 2003 (UDOT)
Construction start Late April 2026
Still to come More widening and barrier work in 2027
Live conditions UDOT Traffic app or udottraffic.utah.gov

What UDOT announced

UDOT's Nov. 12 news release said the department is preparing to open the interchange and that it will open by Nov. 30. The new design carries US-6 over US-89 on a bridge, and drivers will get on and off each highway using new ramps with longer acceleration and deceleration lanes. Separating turning and merging traffic from the high-speed through traffic on US-6, UDOT said, is expected to significantly reduce the risk of serious crashes.

UDOT's project page describes the same layout from the other direction: US-6 stays at its current grade, and US-89 runs through a new underpass beneath it. The page also lists reconstructed turning movements alongside the new ramps.

Advertisement

The Daily Herald reported that the project's primary objective was saving lives, quoting UDOT project manager Tyler Faddis, who lives in Sanpete County and uses the junction himself. Faddis said the interchange will help commuters from Sanpete and Carbon counties. He also told the Herald that incoming weather could slow the opening, but that he hoped to see traffic passing through within a week.

A ceremony without a ribbon

UDOT did not hold a ribbon cutting. Instead, the Daily Herald reported, families sounded bullhorns and then took the first steps through the new underpass. UDOT's release said the event included remarks from a family that lost loved ones in a crash on the highway, and that UDOT gave families shadow boxes holding miniature replicas of the original rock memorial at the junction, which was removed for construction.

According to the Herald, the event was suggested by Amy Marcus, who asked that crash victims' families be invited. Marcus lost her 16-year-old daughter, Katie, and her 12-year-old son, Taylor, in 2014 while driving home to South Ogden from Mt. Pleasant, the paper reported. "It's a huge relief knowing that no one can die again taking a left-hand turn," she told the Herald.

UDOT Deputy Director Lisa Wilson said in the release, "We know that no road improvement can undo a family's loss, but we hope this interchange can help prevent other families" from going through the same thing.

Why this junction

UDOT says five crashes at or near the intersection have killed eight people since 2003. The Herald described Thistle Junction as one of the most dangerous intersections in the state. UDOT's May announcement called it one of the state's busiest junctions.

The problem was the left turn. Drivers coming north on US-89 had to turn left across US-6, a highway that carries heavy truck and recreational traffic at highway speeds between Utah Valley and eastern Utah. The new interchange removes that crossing movement.

How fast it was built

Crews started work in late April. UDOT's project page lists a start of Monday, April 27, and KSL reported on May 8 that the main construction phase had begun with a scheduled completion of Nov. 15. The Herald reported that nine months were cut from the projected construction time because the design engineer added resources and the contractor was given an incentive to finish early, so the interchange could be ready before winter.

The work has not been painless. Starting May 8, UDOT reduced a two-mile stretch of US-6 around the junction to one 10-foot lane in each direction, 24 hours a day, every day including holidays. UDOT warned of delays of up to 1.5 hours on peak holiday travel days and moderate delays on regular Friday and Sunday afternoons. UDOT project manager Eric Rasband said at the time, "This will slow things down, especially on holiday weekends, and we know that's frustrating," adding, "But getting this project done will save lives."

What drivers should expect now

Before it opens. Until UDOT switches traffic onto the new ramps, expect the same one-lane-each-way pattern near the junction. UDOT's project page says delays are likely, especially at peak times, and recommends traveling off-peak, using the zipper merge and checking the UDOT Traffic alert system.

After it opens. Drivers going between US-6 and US-89 will use ramps instead of turning at a stop. Give yourself time to read the new signs the first few trips, and expect crews to return in 2027.

In winter. UDOT's release said opening before winter gives drivers a safer route before snow and ice make canyon travel harder. Spanish Fork Canyon still sees serious crashes in any season. On Tuesday, Nov. 10, a semi rolled over near mile marker 199 on US-6 in the canyon and spilled fuel, KUTV reported. Two people had minor injuries and were released at the scene, and crews were there about two hours. Check conditions before you go, and see our guide to Utah's winter traction law and chains and winter tires for canyon driving.

Advertisement

Thanksgiving week. UDOT has said holidays bring the heaviest canyon traffic. If the interchange opens on schedule, Thanksgiving travelers to Sanpete County, Price or Moab may be among the first to use it, but UDOT has not announced a specific opening day. Watch the UDOT Traffic app.

The rest of the US-6 work

Thistle Junction is one piece of a long-running effort on US-6. UDOT says it has invested more than $150 million in US-6 over the past two decades, including widening, passing lanes, median barriers and intersection upgrades. UDOT's Nov. 12 release lists these other projects:

Project What it includes Status (UDOT)
Diamond Fork to Thistle Junction More than 9,000 feet of median barrier, overhead lighting, drainage Nearly 5 miles complete
Chicken Hollow to Tie Fork $53.4 million: widening, center median barrier, flattening curves, Sheep Creek Road intersection Expected to finish in 2027
Price River to Middle Mountain Bridge and pavement repairs and new guardrail on about 12 miles Expected to finish by year's end

In August 2025, UDOT said its long-term goal is a four-lane US-6. Region 3 Deputy Director Boyd Humpherys said then, "US-6 is a critical route for so many Utahns, and these improvements are about making every trip safer."

If you use the canyon

The junction takes its name from the old railroad town of Thistle. Our guide to Spanish Fork Canyon, Diamond Fork, Sheep Creek and the Thistle site covers the history and the recreation stops along US-6. Heading south on US-89 instead? Our guide to things to do in Sanpete County starts at this junction. For other projects around the valley, see our Utah County road construction guide, and for UDOT's new tool that shows when canyon traction rules apply, read our story on UDOT's online traction tool.

UDOT's project hotline is 801-738-8149, and updates are posted at udotinput.utah.gov/us6thistlesafety.

Sources: UDOT news releases of Nov. 12, 2026, May 6, 2026 and Aug. 14, 2025; UDOT's US-6 and US-89 Thistle Junction project page; the Daily Herald; KSL; and KUTV, all checked Nov. 13, 2026.

Advertisement

Frequently Asked Questions

When does the new Thistle Junction interchange open?
UDOT says the new interchange at US-6 and US-89 will open by Monday, Nov. 30, 2026. UDOT project manager Tyler Faddis told the Daily Herald on Nov. 12 that incoming weather could delay the opening, but he hoped to have traffic using it within a week.
Where is Thistle Junction?
Thistle Junction is in Spanish Fork Canyon, southeast of Spanish Fork, where US-89 splits off US-6 and heads south toward Sanpete County. UDOT describes it as one of the busiest junctions in the state.
What is changing at Thistle Junction?
UDOT is replacing the old T intersection with a grade-separated interchange. US-6 stays at its current level and crosses over US-89, which now runs through an underpass. Drivers enter and leave each highway on new ramps with longer acceleration and deceleration lanes.
Why did UDOT rebuild Thistle Junction?
Safety. UDOT says five crashes at or near the intersection have killed eight people since 2003. The interchange separates turning and merging traffic from high-speed US-6 traffic and removes the left turn from US-89 onto US-6.
Is US-6 still down to one lane at Thistle?
Since May 8, US-6 has been reduced to one lane in each direction for about two miles around the junction, 24 hours a day. UDOT's earlier notices said the restrictions would end when the interchange opens. Check the UDOT Traffic app or udottraffic.utah.gov before you drive.
Is the Thistle Junction project finished?
Not entirely. UDOT's project page says more work will happen in spring and summer 2027 after a winter shutdown, and UDOT's Nov. 12 announcement says more widening and barrier work is planned in 2027.
What else is UDOT doing on US-6?
UDOT lists a $53.4 million project from Chicken Hollow to Tie Fork to widen the highway, add a center median barrier, flatten several curves and improve the Sheep Creek Road intersection, expected to finish in 2027. Nearly five miles of barrier and lighting work between Diamond Fork and Thistle is complete.
How do I get project updates for Thistle Junction?
UDOT's project page lists a hotline at 801-738-8149 and an email address for updates, and it has a sign-up tab on udotinput.utah.gov/us6thistlesafety. For live conditions, use the UDOT Traffic app or udottraffic.utah.gov.

Sources

The facts in this guide were checked against these sources. Hours, fees and rules change, so confirm anything time-sensitive with the source before you go. How we make Provo.com.

  1. UDOT prepares to open new US-6, US-89 interchange in Spanish Fork Canyon, Utah Department of Transportation. Checked November 13, 2026.
  2. US-6 & US-89 Thistle Junction Safety Project, Utah Department of Transportation. Checked November 13, 2026.
  3. US-6 to be reduced to one lane through Nov. for grade-separated interchange project, Utah Department of Transportation. Checked November 13, 2026.
  4. UDOT to add new safety features along US-6, Utah Department of Transportation. Checked November 13, 2026.
  5. Built to save lives: UDOT celebrates completion of new Thistle Junction interchange, Daily Herald. Checked November 13, 2026.
  6. Thistle Junction construction begins in Spanish Fork Canyon, KSL. Checked November 13, 2026.
  7. Two people injured in semi-truck rollover on Highway 6 in Spanish Fork Canyon, KUTV. Checked November 13, 2026.
P
Provo.com News Desk
Newsroom
The Provo.com News Desk covers community news, business openings, civic announcements, and cultural events across Provo, Orem, and Utah Valley. Stories are curated from local outlets, city sources, and primary reporting, then written in our own words to give residents, students, and visitors a faster way to track what's actually happening in the area.