Provo Airport marked a milestone in its terminal expansion on Tuesday, Nov. 10, 2026, with a topping-out ceremony for phases 2 and 3 of the project, ABC4 reported. At the event, airport director Brian Torgersen said the first new gates are currently expected to open in November 2027, with three gates arriving that year and the rest coming before the project's full completion in 2029.
That is a few weeks earlier than the date the airport put in writing in June, and the ten-gate finish line stays in 2029. Nothing about this winter's flight schedule changes.
| Event | Topping-out ceremony, Terminal Expansion Project phases 2 and 3 |
| When | Tuesday, Nov. 10, 2026 |
| First new gates | Expected November 2027 (three gates), per director Brian Torgersen |
| Full build-out | 2029, for ten gates in total |
| Gates today | Five operating gates (four at the 2022 opening, plus one added later) |
| Funding pledged | $140.3 million, as of December 2025 |
| Groundbreaking | Monday, April 14, 2025 |
What a topping out is
A topping-out ceremony marks the completion of a major phase of construction, traditionally by installing the final beam of a building, and organizers use it to recognize the crews doing the work, as ABC4 described Tuesday's event. It is a structural milestone, not an opening. Interior work, systems, finishes, inspections and the move-in of airline equipment all come after.
Provo has done this before. On Thursday, May 20, 2021, crews locked the highest beam of the current terminal into place, a beam signed by the people who made the building possible, KSL reported at the time. That terminal was budgeted at $55 million and opened in 2022. Then-mayor Michelle Kaufusi said at that 2021 ceremony that the building was designed to grow, "potentially out to 10" gates. The expansion that topped out Tuesday is that growth.
What the airport said Tuesday
According to ABC4's report, Torgersen told the crowd that the airport finished its initial terminal build in July 2022 and later started the expansion. He said the first new gates are expected to open in November 2027. ABC4 reported that only three gates are expected to open in 2027, with the remaining gates expected before full completion in 2029.
Utah County Commissioner Skyler Beltran spoke about growth. "Infrastructure is number one issue with our residents and our community," he said, according to ABC4. "We continue to grow. We continue to need new infrastructure," he added, saying the airport has kept up.
ABC4's story contains two figures that do not line up with the airport's own description of the project, so readers should know how to read them. The story refers to "eight new gates" and also describes three new gates on each of the north and south sides. The airport's June 2026 statement to the Lehi Free Press said the North Concourse adds three gates for a total of eight, and the South Concourse adds two more for a total of ten. The most consistent reading is that eight is the gate total after the first new gates open, not the number of new gates. ABC4 also spelled the director's and commissioner's names "Torgerson" and "Skylar"; the Daily Herald and KSL use Brian Torgersen and Skyler Beltran, and this story follows them.
November 2027 or December 2027?
This is the detail most likely to cause confusion, so here is the record:
- Spring 2025 to spring 2026: KSL and the Daily Herald reported that the new gates were expected to open in late 2028. In February 2025, Torgersen described the goal to the Daily Herald as a "ten-gate expansion by 2028."
- June 25, 2026: In a written statement published by the Lehi Free Press, airport communications manager Jenna Ahern said the North Concourse Addition would be "complete and operational by December 2027," and the South Concourse Addition was targeted for 2029.
- Nov. 10, 2026: Torgersen said at the ceremony that the first new gates are expected in November 2027, per ABC4.
Read together, the airport has been consistent about the shape of the plan since June: three gates in late 2027, the last two in 2029. Tuesday's remarks narrow the first date to November. Treat November 2027 as the airport's current target, not a booking date.
What phases 2 and 3 cover
The phase descriptions have shifted as design work moved along, so here is what each source said.
In January 2025, the Daily Herald reported the expansion as a nine-phase project. Phase 1 was the apron, the paved area where aircraft park, expanded so planes could stay overnight. Phase 2 would expand ticketing stations from 10 to 28 and build outbound baggage processing to full capacity. Later phases had no concrete timeline at the time.
In December 2025, Torgersen updated the Provo City Council. According to the Daily Herald, phase one began in April 2025 with the north-side apron. Phase two covers ticket and check-in counters and the baggage-handling system and was already under construction, with its foundation work set to finish in February 2026. Phase three would build gates, among other infrastructure, with foundation work starting once phase two's was done.
Tuesday's ceremony covered phases 2 and 3 together. In the airport's June language, that north-side work is the North Concourse Addition, the part of the project dated to late 2027. The South Concourse Addition, with the final two gates and shell space for a future Customs and Border Protection facility, follows and is targeted for 2029.
Cost and funding
Tuesday's coverage did not include new dollar figures. The most recent breakdown on the record is from December 2025, when Torgersen told the City Council that $140.3 million had been pledged, the Daily Herald reported:
- Utah County: $68.4 million, plus $13 million in bond interest
- Federal Aviation Administration: $20.5 million, plus an anticipated $10 million
- Mountainland Association of Governments: $16.9 million
- State of Utah: $10.5 million
- Provo City: $11 million from the transportation sales tax and $13 million from airport reimbursements
The county's share traces to a January 2025 interlocal agreement. The Daily Herald reported then that the county committed $78 million, paid as $19.5 million up front and $3.9 million a year for 15 years, from its tourism, recreation, cultural and convention (TRCC) tax, with Beltran saying no general fund money was involved. At that point the paper put the total cost at an estimated $140 million.
On the city side, the Provo City Council reapproved $20 million in 15-year transportation sales tax revenue bonds in February 2026, the Daily Herald reported. The council had first approved the bond in December 2025 but held another hearing to satisfy federal tax rules, because the city plans to repay the bond early with airport revenue, and to address lenders' questions about the tax. Torgersen had described the bond in December as bringing revenues already planned for the project forward so they could be used for construction.
Why the airport is building
The demand case has not changed. The airport's June statement said PVU has served more than 3.5 million passengers since the terminal opened in July 2022, and Beltran put 2025 alone at over one million. In early 2025, Torgersen told the Daily Herald the airport was at capacity and could not add routes or airlines until the expansion was done. That is still the practical constraint: until the new gates open, there is little room for a new carrier at peak times.
The plan also includes two gates designed for international arrivals, the Daily Herald reported, and the customs shell space is part of the 2029 phase. No airline has announced international service from Provo, and none can operate it until a federal inspection facility is built and staffed.
What it means if you fly from Provo
- This winter: Same terminal, same five gates, and no new airline announced. Construction is staged so flights keep running, the airport has said.
- Holiday travel: Thanksgiving is Thursday, Nov. 26. With an active job site around the terminal, give yourself extra time at the curb and in the lots, and check airport.provo.gov for parking updates before you leave home.
- Late 2027: The first three new gates are the earliest point where new routes tied to added capacity become realistic.
- 2029: Ten gates, plus the customs shell.
If you are deciding between Provo and Salt Lake for a trip this season, our PVU vs. SLC comparison walks through the tradeoffs, and the flying from Provo Airport guide covers parking, security timing and the terminal. Every current destination and the airline that flies it is in our Provo Airport route list.
This story picks up where our earlier coverage left off: the June 2026 expansion report on the funding and first phase, and the September timeline update on how the airport split the schedule into a 2027 phase and a 2029 phase.
Sources: ABC4 (KTVX), "Provo Airport terminal expansion project reaches major construction goal," Taylor Bolar, Nov. 10, 2026 (read via its Yahoo News syndication); Lehi Free Press, June 25, 2026, quoting airport communications manager Jenna Ahern; Daily Herald reporting by Jacob Nielson (Jan. 30, 2025; Dec. 2, 2025; Feb. 11, 2026) and Curtis Booker (Feb. 14, 2025); KSL reporting by Cassidy Wixom (April 14, 2025) and Carter Williams (May 20, 2021). Dates for the new gates are the airport's targets and may change.
Related Guides
- Provo Airport gate timeline: 8 gates by Dec 2027, 10 by 2029 - how the airport split the schedule in June
- Provo Airport expansion, June 2026 - mainline jets, funding and the first phase
- Flying from Provo Airport - parking, security timing and the terminal
- PVU vs. SLC: which airport should you fly from? - the decision, route by route
- Provo Airport route list - every destination and the airline that flies it
- Jobs at Provo Airport - who hires there as the airport grows
- West Provo guide - the neighborhoods around the airport
Frequently Asked Questions
What happened at Provo Airport on Nov. 10, 2026?
When will Provo Airport's new gates open?
How many gates will Provo Airport have when the expansion is done?
Did the airport change its opening date?
How much does the Provo Airport expansion cost and who is paying?
Is Provo getting international flights?
Will construction affect my flight from Provo?
Where can I read more about the Provo Airport expansion?
Sources
The facts in this guide were checked against these sources. Hours, fees and rules change, so confirm anything time-sensitive with the source before you go. How we make Provo.com.
- Provo Airport terminal expansion project reaches major construction goal (ABC4, via Yahoo News syndication), ABC4 / KTVX. Checked November 11, 2026.
- Officials say Provo Airport expansion progressing on schedule, as passenger count surges, Lehi Free Press. Checked November 11, 2026.
- Provo Airport director provides expansion update, discusses proposed transportation sales tax bond with Provo City Council, Daily Herald. Checked November 11, 2026.
- Provo City Council reapproves $20 million sales tax revenue bond for airport expansion, Daily Herald. Checked November 11, 2026.
- Utah County pledges $78 million to help fund next phase of Provo Airport expansion, Daily Herald. Checked November 11, 2026.
- City Council establishes Provo Airport as its own department; Torgersen appointed as director, Daily Herald. Checked November 11, 2026.
- Provo Airport breaks ground on 3-year expansion project, KSL. Checked November 11, 2026.
- New Provo airport terminal expected to arrive on time despite minor bumps, KSL. Checked November 11, 2026.