Skip to main content
Your trusted guide to Provo, Orem & Utah Valley
Overhead aerial view of a yellow tracked excavator parked on bare graded earth criss-crossed with tire tracks at a construction site

The Point: What Is Actually Being Built on the Old Prison Site

The 600-acre former Utah State Prison site is becoming a state-owned district called The Point. What has actually been built, what is only proposed, why it sits in Salt Lake County rather than Utah County, and what it means for the northern edge of Utah Valley.

Drive north out of Utah Valley on I-15 and, just as the freeway climbs through the gap in the ridge, the land on your right opens into several hundred acres of nothing much. Graded dirt. New roadway. Utility trenching. A few pieces of heavy equipment.

For seventy years that ground held the Utah State Prison. It is now the largest state-directed redevelopment project Utah has ever attempted, and it has a name: The Point.

If you live in Provo, Orem, Lehi or anywhere between, this project will affect your commute, your housing market and your job market — and almost everything most people believe about it is slightly wrong, starting with which county it is in.

The fact that corrects most of the confusion

The Point is in Salt Lake County, not Utah County.

Advertisement

The old prison stood in Draper. Draper is Salt Lake County. The 600 acres being redeveloped sit on the Salt Lake side of the ridge, and the adjacent groundbreaking work has extended into Bluffdale, which is also Salt Lake County.

The confusion is understandable, because "Point of the Mountain" is a geographic name for the gap where Utah County and Salt Lake County meet, and a name that references neither county gets claimed by both. Ask around Lehi and you will hear the project described as local. Ask in Draper and it is obviously theirs.

Draper is right. This matters practically rather than pedantically: the property taxes, the municipal approvals and the direct fiscal benefit land on the north side of the line. What lands on the Utah County side is the traffic, the housing pressure and the labor-market pull.

So the accurate framing for anyone reading this from Utah Valley is not "our new development." It is "the enormous thing being built immediately over our northern boundary, which we will absorb the effects of without collecting the tax base."

Seven decades of what was there before

The Utah State Prison opened at the site in the early 1950s and operated there for roughly seventy years. For most Utahns of a certain age it was simply a fixed feature of the drive — the fenced compound and guard towers visible from the freeway, unremarkable through sheer familiarity.

It closed in the summer of 2022, when the state completed a replacement facility in Salt Lake City. The incarcerated population, numbering in the low thousands, was transferred to the new prison.

Demolition began in late 2022. The first tower came down in front of an invited crowd that November; the last guard tower was toppled the following August, ending the demolition phase. The majority of the material was recycled rather than dumped, and some of the demolition crew were people who had previously served time at the facility they were tearing down — a detail widely reported at the time and hard to improve on as a piece of symbolism.

Advertisement

The one building that was spared

Everything came down except a chapel.

The prison chapel, dedicated in the early 1960s, was built substantially by incarcerated men, using their own money together with donations from community and religious organizations. When redevelopment planning reached the question of what to keep, the Land Authority board voted to preserve it.

It is a small decision against a project of this size, and it is the one most likely to still matter in fifty years. A district built on a cleared site has no history at all unless somebody deliberately keeps a piece of it, and the chapel is what somebody kept.

Why the prison moved at all

This is worth understanding because it explains why the project exists.

The old facility was aging and expensive to maintain, and the argument for replacing it was made on corrections grounds. But the decision was inseparable from real estate. The state owned 600 contiguous acres of flat, freeway-adjacent land in the middle of the fastest-growing tech corridor in the Mountain West, and it was using that land to house a prison.

Moving the prison converted an operational cost center into what officials have repeatedly called the most significant economic development opportunity in state history. Whether the replacement facility's cost was justified is a live political question that has never fully settled. The land opportunity was never seriously disputed.

A landowner that is not a city

In 2018 the Utah Legislature created the Point of the Mountain State Land Authority to plan and oversee redevelopment of the site.

This is the structural oddity at the heart of the project, and it is why the thing behaves differently from ordinary development. Normally a private landowner proposes and a city approves. Here the state is the landowner, acting through a board that mixes state legislators with local elected officials and agency executives.

That arrangement draws a recurring objection — why is the state in the development business at all? — which the project's own backers have acknowledged and answered publicly. Their argument is that a single owner of 600 contiguous acres can plan coherently in a way that fragmented private ownership cannot, and that the public interest in a site this consequential justifies public control of the master plan.

The counterargument is that governments are not especially good at development, and that public ownership concentrates risk on taxpayers. Both positions are reasonable. Neither has been settled by results yet, because the results do not exist.

Ten thousand Utahns and a framework plan

Before any building was designed, the Land Authority ran a multi-year planning and public-input process. The resulting framework plan was approved in 2021 and drew on input from more than ten thousand people.

That number gets cited often, and it deserves a caveat. Broad public input shapes goals — walkability, open space, transit, housing affordability — far more than it shapes buildings. The framework plan is a statement of intent. The actual district emerges from land deals, financing terms and construction economics negotiated years later, which is where plans usually change.

Read the framework plan as the promise. Judge the project against it later.

"15-minute city," decoded

The framework adopted the phrase 15-minute city, and it has followed the project through every subsequent news cycle.

Stripped of the branding, it means a simple thing: the district is designed so that daily needs sit within roughly a fifteen-minute walk of its center. Housing near jobs. Retail near housing. Transit near both. Parks people can reach without driving.

Two honest observations.

First, it is genuinely unusual to attempt this from scratch in an American suburb. Existing suburbs are hard to retrofit because the street network and parking requirements are already built. A blank 600 acres is the rare case where the geometry can be set deliberately.

Second, the phrase has picked up political baggage nationally that has nothing to do with what is being built here. It describes a walking distance, not a restriction on movement. If you encounter heated claims about the term, they are almost certainly not about this project.

What Phase 1 actually contains

Phase 1 is the first hundred acres or so, and it is the part with real agreements behind it.

The Land Authority signed a development agreement in late 2023 with its private-sector partner — a group formed from Lincoln Property Company, Colmena Group and Wadsworth Development Group, presented under a joint venture name. The announced private investment figure was roughly $2.3 billion.

The published components of Phase 1 include:

Treat every number here as a planning figure. Phased developments revise unit counts and building mixes routinely between announcement and completion, and this one is expected to build out over decades.

Why a road was the headline

The moment that actually mattered was less photogenic than any rendering: the extension of Porter Rockwell Boulevard.

State leaders held a ceremonial groundbreaking for it in December 2024, and the Land Authority's planners described the road as the "backbone" infrastructure the rest of the district depends on. Gas lines, water lines and other utility work followed a similar sequence.

This is how large developments genuinely begin, and it is worth knowing because it gives you a reliable way to read progress. Renderings are cheap and can be published years before anything happens. Roads and buried utilities are expensive, are built by contractors under signed agreements, and are visible from the freeway. When you want to know whether a megaproject is real, watch the infrastructure, not the images.

The housing question, without the spin

The housing element is the part most relevant to anyone reading this from Utah Valley, and it deserves care.

Phase 1's residential component has been described as more than three thousand units, weighted toward multi-family, with a subset income-restricted. Separately, the Land Authority has moved to bring in developers for a section of for-sale housing in what it calls the River District — a shift in emphasis, because the early phase leaned rental.

Three honest points.

It is a meaningful number and a small share of the problem. Several thousand units matter. Set against the Wasatch Front's housing shortfall, they are a contribution rather than a solution.

"Affordable" is a technical term. Income-restricted units are priced against area median income under program rules. They are not the same as cheap, and the qualifying thresholds decide who benefits.

New construction in a marquee district is rarely the bottom of the market. The realistic effect on Utah Valley is indirect: added regional supply eases pressure at the margin, and the district's jobs pull demand northward.

What it means for the northern edge of Utah Valley

For Utah County, The Point is best understood as an intensification of a corridor that was already intensifying.

The stretch of I-15 through the gap is among the most congested in the state at weekday peaks — heavy northbound in the morning, heavy southbound in the evening — because tens of thousands of people already live on one side of the ridge and work on the other. Our guide to Lehi and Provo as places to live covers that daily reality in more detail.

Adding a district planned for thousands of homes and tens of thousands of jobs pushes in two directions at once. More activity at the gap means more trips. But a district where housing sits beside employment generates fewer long commutes than the same growth scattered across distant subdivisions.

Which effect dominates depends almost entirely on whether transit and the internal street network arrive on the schedule the plan assumes. That is the thing to watch, and it is genuinely uncertain. Anyone telling you confidently that traffic will get better, or that it will become impossible, is guessing.

Proposal versus plan: a decoder

More nonsense circulates about this project than almost any other in the state, because a state-owned blank slate attracts proposals. Here is how to tell the categories apart.

Under construction means infrastructure is in the ground under a signed agreement. Porter Rockwell Boulevard qualifies.

Under agreement means a development contract exists with a named partner and a financing figure. Phase 1 qualifies.

Under study means someone was hired to assess feasibility. The Land Authority commissioned a study of advanced air mobility — vertiports, air taxis, drone delivery — which tells you the question was asked, not that any of it is coming.

Proposed by outside parties is the loosest category and generates the loudest coverage. A 300-foot "Statue of Responsibility" was floated for the site and drew strong reactions in both directions. Major-league sports have been mentioned by state officials in the general context of the area. None of that is a plan.

Apply this test to any Point headline and most of the confusion resolves itself.

The dates that actually happened

Leadership changed partway through: the executive director who ran the project from 2019 departed in 2024, and a successor was appointed that autumn after a national search.

How to follow it without relying on headlines

The Land Authority publishes board meeting materials, plan documents and solicitations on its own site, and its board meetings are public. That is the substantive record.

Utah's public notice system is the other route, and it is the one most people do not know exists — the state maintains a central register of public meeting notices and agendas for public bodies. Our guide to finding and following public meetings explains how to use it, and the same approach works for following Provo City Council on local matters.

The general principle, which applies to every big project: the agenda packet is more reliable than the press release, and both are more reliable than the rendering.

Is there anything to see?

Not really, and it is better to say so plainly than to send you on a pointless drive.

The site is earthworks and new roadway. There is no visitor center, no tour and nothing to walk. That will change as buildings go up, but it has not changed yet.

If you want a genuine reason to stop near the gap, the ridge above it is one of the best-known paragliding sites in the country, thanks to reliable thermals off the slope, and watching from the ground costs nothing. Our guide to paragliding at Point of the Mountain covers where to park and when the air is worth watching.

The honest summary

The Point is real, it is large, and it is early.

The infrastructure is genuinely under construction, the Phase 1 agreement is genuinely signed, and the money behind it is genuinely committed. It is not vaporware. Equally, it is a decades-long build in which almost every visible element still exists as a plan, and plans of this size change.

For Utah Valley the practical stance is neither excitement nor alarm. It is attention. Something consequential is being built immediately over the county line, its effects will cross that line freely, and its tax base will not. Knowing which parts are under construction, which are under agreement, and which are merely somebody's idea is most of what it takes to read the news about it accurately.

Related Guides

Advertisement

Frequently Asked Questions

Is The Point in Utah County or Salt Lake County?
Salt Lake County. This is the single most common misunderstanding about the project. The former Utah State Prison stood in Draper, which is in Salt Lake County, and the 600 acres being redeveloped sit on the Salt Lake side of the ridge. Point of the Mountain is the name for the gap where the two counties meet, and because the name contains no county reference, people on both sides assume it belongs to them. Utah County's boundary is close enough that the project will change traffic, housing demand and job patterns at the valley's northern edge, but the land, the tax base and the local approvals are not Utah County's.
What was on the site before?
The Utah State Prison, which operated at the site for roughly seven decades beginning in the early 1950s. It closed in the summer of 2022 when the state finished a replacement facility in Salt Lake City, and demolition ran from late 2022 into 2023, ending with the toppling of the last guard tower. One structure was deliberately spared: the prison chapel, which the governing board voted to preserve. Most of the demolition material was recycled rather than landfilled.
Who owns and controls The Point?
The land is state-owned and is overseen by the Point of the Mountain State Land Authority, an entity the Utah Legislature created in 2018 specifically to plan and redevelop the site. Its board mixes state legislators with local elected officials and agency executives. The Land Authority does not build the buildings itself. It selected a private-sector development partner — a group formed from Lincoln Property Company, Colmena Group and Wadsworth Development Group — to finance and construct the first phase.
What is a 15-minute city, and is that what this is?
The phrase describes a planning goal rather than a building type: the aim is that daily needs — work, housing, groceries, recreation, transit — sit within roughly a fifteen-minute walk of the district's center. The Point's framework plan adopted that language early and it has stuck in coverage of the project. It is worth reading as an aspiration being designed toward, not a delivered fact. Whether the finished district functions that way depends on decisions still being made about density, parking, transit service and the mix of ground-floor uses.
How many homes will be built there?
The first phase has been described as more than three thousand residential units, with a portion designated as income-restricted, alongside offices, retail, entertainment space and parks. Separately, the Land Authority has sought developers for a section of for-sale housing in what it calls the River District. Treat all unit counts as planning figures rather than guarantees. Large phased developments routinely revise unit mix and totals between announcement and construction, and this one is expected to build out over decades.
When will it be finished?
There is no single completion date, and any source giving you one is compressing a multi-decade project into a headline. Infrastructure work — roads, utilities, gas lines — began first, and the extension of Porter Rockwell Boulevard was treated as the backbone that everything else depends on. Officials have discussed first occupancy in the late 2020s for early phase-one buildings. The full district is a generational build, and the people planning it say so openly.
How will The Point affect traffic through the Point of the Mountain?
The honest answer is that nobody knows the net effect yet, and be skeptical of confident claims in either direction. The stretch of I-15 through the gap is already among the most congested in the state during weekday peaks. Adding thousands of homes and tens of thousands of planned jobs adds trips. The counterargument built into the plan is that a district where people can live near work generates fewer long commutes than the same growth spread across distant suburbs. Both things can be true, and the outcome depends heavily on whether transit and the internal street network arrive on schedule.
Can I visit or see the site?
There is nothing to tour. The site is an active construction and infrastructure project, not an attraction, and for now the visible experience is earthworks and roadway from the freeway. If you want a genuine reason to stop near the gap, the paragliding flight park on the ridge is a long-standing public site and a much better use of an afternoon. The Land Authority publishes board meeting materials and plan documents, which is the substantive way to follow what is happening.
JoAnn Giordano
JoAnn Giordano
Editor-in-Chief
JoAnn Giordano is the editor-in-chief of Provo.com. Having lived in and around Utah Valley for years, she leads the site's editorial direction with a focus on the comprehensive, honest local coverage that helps residents, students, and newcomers feel at home. When she's not shaping Provo.com's restaurant and neighborhood coverage, she's exploring the valley's trails and tracking down the best new spots on Center Street.